In this section the progress and results achieved are depicted through simple graphical tools and tables. Details on activities and deliverables are available in Documents.
The following table shows a summary of the progress of the actions, reporting information on their planned and actual starting and end dates, the percentage of the work done, the status of the action (regular, delay, ahead, completed), comments on relevant aspects and problems encountered in the implementation process.
Summary Report
Action |
Start Date
Planned
Actual
|
End Date
Planned
Actual
|
Progress (P%) |
Status | Comments | |||
---|---|---|---|---|---|---|---|---|
A1 | State of the art on real time noise mapping systems | 2014-09-01 | 2014-09-01 | 2014-12-31 | 2015-02-05 | 100% | Completed | |
A2 | Road networks analysis and pilot areas location | 2014-09-01 | 2014-09-01 | 2015-01-31 | 2015-02-06 | 100% | Completed | |
B1 | Sizing the monitor network | 2014-09-01 | 2014-09-01 | 2015-09-30 | 2015-12-03 | 100% | Completed | |
B2 | Monitoring network hardware development | 2015-04-01 | 2015-01-02 | 2016-07-30 | 2017-05-01 | 100% | Completed | |
B3 | Development of the ANED (Anomalous Noise Event Detection) algorithm | 2015-04-01 | 2015-03-03 | 2016-06-30 | 2016-10-01 | 100% | Completed | |
B4 | Software development for dynamic noise mapping | 2015-05-01 | 2015-02-01 | 2018-06-30 | 2018-08-11 | 100% | Completed | |
B5 | Pilot Area 1 (Milan): system implementation | 2015-07-01 | 2015-06-01 | 2018-10-31 | 99% | On schedule | ||
B6 | Pilot Area 2 (Rome): system implementation | 2015-07-01 | 2015-06-01 | 2018-10-31 | 99% | On schedule | ||
B7 | System test and fault analysis | 2017-01-01 | 2017-01-02 | 2018-12-31 | 98% | On schedule | ||
B8 | Future system upgrade | 2018-07-01 | 2018-11-05 | 2018-09-30 | 2019-03-26 | 100% | Completed | |
B9 | Guideline to real time noise mapping | 2017-04-01 | 2017-12-04 | 2019-03-31 | 95% | On schedule | ||
C1 | Monitoring public response and user ability in consulting and managing the system | 2017-04-01 | 2017-09-30 | 2018-12-31 | 2019-05-06 | 100% | Completed | |
C2 | Cost-benefit analysis of the system on a large scale | 2018-03-01 | 2018-03-01 | 2018-07-31 | 96% | On schedule | ||
C3 | Future vision on system applications | 2018-10-01 | 2018-11-05 | 2018-12-31 | 2019-04-11 | 100% | Completed | |
D1 | Dissemination | 2014-07-01 | 2014-07-01 | 2019-06-30 | 98% | On schedule | ||
D2 | Dissemination – Special Events | 2015-10-01 | 2014-07-01 | 2019-06-30 | 97% | On schedule | ||
E1 | Coordination and project management | 2014-06-01 | 2014-06-06 | 2019-09-30 | 96% | On schedule | ||
E2 | Networking with other projects | 2015-04-01 | 2014-12-01 | 2018-12-31 | 2019-06-06 | 100% | Completed | |
E3 | Future development – After Life Communication Plan | 2018-10-01 | 2019-03-29 | 2019-03-31 | 98% | On schedule |